The most recent updates are listed below. View the archive of all updates here
March 27, 2026
Over the past few weeks, the contractor has been excavating for the East Main Street road realignment along the front of the Kent United Church of Christ and continuing storm sewer installation on Horning Rd. The storm sewer work is expected to last into mid-April and then crews will begin installing new curb, driveway aprons, sidewalk, and asphalt pavement on Horning Rd.
The gas main relocation and replacement work continues with crews concentrating on East Main Street between Depeyster and Lincoln streets. This work is expected to be completed in about another month, depending on weather and other factors.
Work has started on restriping the faded pavement lines in the project area, including crosswalk locations.
If you’re traveling East Main St. in the construction area, please remember to slow down, pay attention to the posted signs, and use caution when entering and exiting the temporary roundabout.
Questions about the East Main Street project can be directed to Jon Giaquinto in the City Engineering Division at
Jon.Giaquinto@KentOhio.gov or 330-678-8106. You can also send your email address to Giaquinto if you would like to receive email updates.
.
March 10, 2026
The gas line installation on Horning Rd. has been completed and now surface restoration work is underway.
Wartko Construction will have three crews on site working in different areas this week to complete the restoration work. The work includes backfilling crossings and installing pipe crossings at various intersections. This work may cause some detours and flaggers directing traffic in the project area.
Kenmore Construction is scheduled to work on water main adjustments and storm sewer installation on Horning Rd. over the next several weeks. The storm sewer work will generally follow the same area as the gas line work from Loop Rd. to Theatre Drive and then to East Main St.
With the warmer weather, Kenmore is also planning to remark the faded pavement markings throughout the construction area over the next few weeks.
If you're traveling East Main St. in the construction area, please remember to slow down, pay attention to the posted signs, and use caution when entering and exiting the temporary roundabout.
Questions about the East Main Street project can be directed to Jon Giaquinto in the City Engineering Division at Jon.Giaquinto@KentOhio.gov or 330-678-8106. You can also send your email address to Giaquinto if you would like to receive email updates.
Feb. 10, 2026
Work has started on the first phase of relocating gas lines in the project area. Don Wartko Construction is doing the work for Enbridge and as early as Wednesday (Feb. 11), crews are expected to start installing the new gas line on East Main St. between Overlook Dr. and the United Methodist Church.
Please be aware that intermittent delays may occur on East Main while this work is being done. One lane of traffic with flaggers will be maintained and areas of the sidewalk along the north side of East Main may be blocked while work is in progress. The contractor will have extra workers on hand to assist pedestrians.
If you’re traveling in the construction area of East Main Street, please remember to slow down, pay attention to the posted signs, and use caution when entering and exiting the temporary roundabout, especially during inclement weather.
Questions about the East Main Street project can be directed to Jon Giaquinto in the City Engineering Division at Jon.Giaquinto@KentOhio.gov or 330-678-8106. You can also send your email address to Giaquinto if you would like to receive email updates.